FINAL REPORT OF
THE AUDITOR-GENERAL
ON THE
HINDMARSH SOCCER STADIUM
REDEVELOPMENT PROJECT


Downloads Available - in PDF format

To open/read a file on-line in Adobe Acrobat, click on the link below.

To Download
the file :-
Netscape : right click on the link and select "Save Link As"
; or,
Internet Explorer  : right click on the link and select "Save Target As".

Part 1 - 175K
Part 2 - 964K
Part 3 - 1,544K


To read the text of any section of the report on-line, with your browser,
click on the required link below.


Part 1
Key Findings and Recommendations

MEMORANDUM TO PARLIAMENT

GLOSSARY

CHAPTER 1 – INTRODUCTION

    Why the Examination was Undertaken
    Conduct of Examination
    Scope of Examination
            Legal
            Administrative
            Financial
    Natural Justice and Procedural Fairness
    Standard of Proof
    Allegation that Documents were Shredded

CHAPTER 2 – OVERVIEW OF KEY FINDINGS AND ISSUES IN THIS REPORT

    Introduction
    A Note of Importance
    Costs
    Benefits
    Policy Decisions
    In a Nutshell What Went Wrong
            Mr Ingerson
            The South Australian Soccer Federation
            Mrs Hall
    The Undermining of the Public Works Committee Process
    Other Major Failures of Due Diligence
            Inadequate Feasibility and Cost Benefit Analysis
            Cabinet Submissions Inadequate Basis for Decision
    Failure to Achieve Key Objective
    Ownership and Management Issues
    The Effect of the legal arrangements on Soccer Organisations
            The Soccer Federation
            Adelaide City
            West Adelaide
    Mrs Hall’s Role as Ambassador for Soccer
            The Various Roles Held by Mrs Hall
            Mrs Hall: A Conflict of Interest and Duty
    A General Comment by Way of Clarification

CHAPTER 3 – SUMMARY REPORT ON TERMS OF REFERENCE

    Terms of Reference I and II 
            Initiation and Approval 
            Public Works Committee Process 
            Direction and Control 
            Ownership and Management
    Term of Reference III(a) 
    Term of Reference III(b) 
            Purchase of Hindmarsh Stadium Site 
            Soccer Federation Agreement
            Adelaide City Agreement
            Effect on the Stage 1 Project Documents 
            Document for Hosting Olympic Soccer Tournament 
    Term of Reference IV 
            Conflicts of Interest
            Appropriate Processes 

CHAPTER 4 – RECOMMENDATIONS

    Overview
    Project Management and Control 
            Compliance 
            Evaluation of Public Sector Projects
            Coordination and Communication Between Ministers and Agencies
            Agency Advice
            Preparation of Cabinet Submissions for Public Sector Projects 
    Public Works Committee Process 
    Contract Management 
    Ongoing Risk Assessment

Part 2
Chronology

CHAPTER 5 – INTRODUCTION TO PART 2 

    Overview

CHAPTER 6 - 1988 TO DECEMBER 1994

    September 1988 - "A Major Facility Development"
    April 1989 - Feasibility Study for Soccer: Hindmarsh v Gepps Cross 
    August 1989 - $3.9 million Package
    November 1989 – $6.2 million Estimate 
    March 1990 - Project Justification Report 
    May 1991 - Proposal for Partial Upgrade for 1993 World Youth Championships 
    July 1993 – Abolition of the Department of Recreation and Sport 
    August 1993 – Merger of Hindmarsh and Woodville Councils 
    September 1993 - Sydney 2000 Olympics Win 
    November 1993 – SACON Abolition and Reconstitution 
    9 December 1993 – Mr Crafter’s Letter to Soccer Federation 
    14 December 1993 - Change of Government 
    January 1994 - Proposal for Government to Take Over Lease 
    February 1994 - Soccer Federation’s Submission to Minister Oswald
    February 1994 - SACON Preliminary Feasibility Estimate of $30.75 million 
    March 1994 - Mr Ellis’ Review of Proposals to Upgrade Hindmarsh 
    May 1994 - Cabinet Submission
    May 1994 - Request for $6.7 million Grant 
    30 June 1994 – Establishment of the Department for Building Management 
    October 1994 - FIFA Requirements as to Temporary Facilities 

CHAPTER 7 - JANUARY TO DECEMBER 1995 

    30 January 1995 – SOCOG Letter to the Premier of South Australia
    February 1995 - Early Estimates of Cost of Hosting Olympic Soccer
    20 April 1995 – Budget Sub-Committee Approval
    April 1995 - First Involvement of the Crown Solicitor’s Office
    28 April 1995 - Memorandum of Understanding with the Soccer Federation
    29 April 1995 – Memorandum of Understanding Between the Federation and the NSL Clubs 
    1 May 1995 – Council of Clubs Authorisation of Soccer Federation Loan
    1 May 1995 - Cabinet Approval
    18 May 1995 - Committees for Redevelopment Established 
    20 July 1995 - First Meeting of the Executive Committee
    August 1995 - Soccer Federation Attempts to Increase Budget
    1 September 1995 - Appointment of Department for Building Management as
Project Manager 
    4 September 1995 - Department for Building Management Project Brief
    20 September 1995 - Tender Process for Appointment of Primary Consultant 
    30 October 1995 - Establishment of Services SA 
    8 November 1995 - Appointment of Woods Bagot 
    8 November 1995 - Woods Bagot Preliminary Design Work
            Project Definition 
            Assessment of Future Development Options
            Identification of Need for Land Acquisition 
            Financial Examination 
            Identification of Preference to Redevelop Western Side 

CHAPTER 8 - DECEMBER 1995 TO MAY 1996 

    Late 1995 - Appointment of Mrs Hall as Ambassador for Soccer 
    22 December 1995 - Change of Minister for Recreation, Sport and Racing 
    18 January 1996 - Woods Bagot’s First Project Report
    22 January 1996 - FIFA Letter About Pitch Size 
    February 1996 - Establishment of Hindmarsh Stadium Redevelopment Committee 
    22 February 1996 - Change of Title for Services SA 
    23 February 1996 - Soccer Federation Lease
    February 1996 - 2000 Olympic Soccer Qualifying Tournament
    February 1996 - Debt Servicing Costs During Construction 
    6 March 1996 - Change from Eastern to Western Grandstand
    8 March 1996 - Mr Scott Meets with SOCOG
    18 March 1996 - Cabinet Approves Mrs Hall’s Appointment as Parliamentary Secretary to
Mr Ingerson 
    20 March 1996 - Mr Ingerson’s First Briefing
            Land Acquisition 
            Town Planning
            Traffic Planning 
    21 March 1996 - Establishment of Adelaide Olympic Bid Committee 
    21 March 1996 - Issues Identified by Treasury and Finance 
    April 1996 - Soccer Federation Complaint to Soccer Australia about the Bid Process 
    2 April 1996 – Involvement Again of the Crown Solicitor’s Office 
    8 April 1996 – Funding of Interest During Construction 
    April 1996 - Draft Ernst & Young Report 
    29 April 1996 - Cabinet Approval for Western Grandstand Redevelopment and
$8.125 million Budget 
            Cabinet Decision
            Preparation of the Submission
            Departure from April 1995 Memorandum of Understanding
            Inaccuracies in Cabinet Submission
                Misdescription of the Soccer Federation Commitment 
                Inadequate Summary of Ernst & Young Report
            Land Acquisition 
            Interest Cost During Construction
            No Comment by Treasury and Finance or the Crown Solicitor’s Office
    1 May 1996 - Meeting of the Council of Clubs
    1 May 1996 - Presentation of Master Plan by Woods Bagot 
    2 May 1996 - Article in the Advertiser
    3 May 1996 - The Department of Treasury and Finance’s Further Instructions 
            Financial Advice
            Policy issues 
    10 May 1996 - Further Instructions for the Crown Solicitor’s Office
    22 May 1996 - Retainer of National Portfolio Strategies
    23 May 1996 - First Meeting of the Executive Group of the Hindmarsh Stadium
Redevelopment Committee
    30 May 1996 - Instructions from Treasury and Finance to the Crown Solicitor’s Office 
    31 May 1996 - Treasury and Finance Response to Mr Scott’s Request to Work Together

CHAPTER 9 - JUNE TO JULY 1996

    June 1996 - Public Works Committee Deliberations on Stage 1
            Submission to Public Works Committee 
            12 June 1996 Hearing before the Public Works Committee 
    June 1996 - Letter to Council
    13 June 1996 - The Crown Solicitor’s Office Briefing on Land Acquisition 
    24 June 1996 - The Department of Treasury and Finance Analysis of the Funding Offers 
    25 June 1996 - Second Meeting of Executive Group
    26 June 1996 - Estimates Committee
    28 June 1996 - Pressure on the Crown Solicitor’s Office for the Documents
    July 1996 - Mr Scott’s Birmingham Trip 
    1 July 1996 - Final Ernst & Young Report 
    1 July 1996 - Financial Information from the Soccer Federation
    2 July 1996 - First Draft of Funding Deed 
    4 July 1996 - Second Draft of Funding Deed 
    5 July 1996 - Treasurer’s Briefing on Concerns Over Funding Arrangements 
    8 July 1996 - Treasurer’s Agreement that Funding Shortfall can be Met from the Sport and
Recreation Fund 
    9 July 1996 - Presentation to Council of Redevelopment Proposal 
    9 July 1996 - SOCOG Invitation for Expression of Interest and Technical Questionnaire 
            The Questionnaire
            Preparation of Adelaide’s Bid 
            Table of SOCOG/FIFA Requirements 
    10 July 1996 - Cabinet Submission 
    10 July 1996 - Reconvening of the Public Works Committee 
    10 July 1996 - Mr Scott’s Request to the Crown Solicitor’s Office to Resolve Funding Deed
Issues Urgently 
    11 July 1996 - Further Instructions from the Minister for Recreation, Sport and Racing on the
Terms of the Funding Deed 
    11 July 1996 - Crown Solicitor’s Office Advice to Mr Scott
    12 July 1996 - Crown Solicitor’s Office Requirement for Quantification of the Shortfall
    12 July 1996 - Treasury’s Response to Mr Scott’s Minutes and Response of the Crown
Solicitor’s Office 
    15 July 1996 - Crown Solicitor’s Office Advice on Who Should be the Principal to the
Construction Contract 
    15 July 1996 - Redevelopment Committee Meeting 
            Endorsement of Project Consultancy Fees 
            Council 
    16 July 1996 – Attorney-General’s Meeting With the Minister for Recreation, Sport
and Racing 
    17 July 1996 - The Crown Solicitor’s Office Discovery that Lease Executed
    17 July 1996 - Cabinet Note Detailing Expenditure to Date
    17 July 1996 - Public Works Committee Letter to Minister for Recreation, Sport and Racing
    24 July 1996 - Discussion Between the Crown Solicitor’s Office and Council About Land
Ownership Issues 
    29 July 1996 - Crown Solicitor’s Office Response to Public Works Committee Request 
            First minute to the Minister for Recreation, Sport and Racing 
            Accompanying Minute
            Final Minute to the Minister for Recreation, Sport and Racing 

CHAPTER 10 - AUGUST TO SEPTEMBER 1996 

    1 August 1996 - Circulation of Revised Funding Deed 
    2 August 1996 - Retainer of Woods Bagot for Stage 1 Design Work 
    6 August 1996 - Value Management Study 
    8 August 1996 - Crown Solicitor’s Office Further Complaint After Meeting with the
Soccer Federation
            Divergent Instructions 
            No Cabinet Approval or Consideration by Treasury
            Government or Private Project 
            Whether Soccer Federation’s Contribution Quarantined to Levies 
            Unreliability of the Ernst & Young Report 
            Mortgage over Lease 
            Unconditional Treasurer’s Guarantee 
    8 August 1996 - Crown Solicitor’s Office Letter to Council 
    12 August 1996 - Council Resolution to Establish Advisory Committee 
    13 August 1996 - Woods Bagot Review of Value Management Study Findings
    13 August 1996 - Mr Scott’s Request for Softer Approach in the Guarantee 
    14 and 15 August 1996 - Circulation of Cabinet Submission for Comment 
    19 August 1996 - Further Comments from the Crown Solicitor’s Office and Treasury 
    19 August 1996 - Cabinet Final Approval of Stage 1 Funding Arrangements and
Appointment of Construction Manager 
            Funding 
            Deed of Guarantee 
            Principal in the Construction Contract 
            Construction Manager
            Land Acquisition 
    20 August 1996 - Letter of Nomination to National Portfolio Strategies 
    23 August 1996 - Council’s Consent for Redevelopment 
    23 August 1996 - Hansen Yuncken Pty Ltd Retainer 
    26 August 1996 - Council’s Support for Development Application 
    27 August 1996 - Executive Group Deferral of Pitch Upgrade 
    28 August 1996 - The Public Works Committee’s 33
rd Report
            Car Parking 
            Procurement Method for Contract Delivery 
            Land Ownership 
            Project Justification 
    29 August 1996 - Licence Agreement Between Soccer Federation and the NSL Clubs 
    30 August 1996 - Council’s Letter to Mr Ingerson About Nominee for Advisory Committee 
    September 1996 - Adelaide’s Bid to SOCOG 
            Discussions with SOCOG Representatives
            Lodgment of Final Bid 
    15 September 1996 - Treasury and Finance Approval of Shortfall in Sport and Recreation
Budget
    16 September 1996 - Nomination of Mrs Hall for Council Advisory Committee 
    19 September 1996 - Rider Hunt Briefing on Cost Estimate for Additional
Permanent Grandstands 
    19 September 1996 - Executive Group Deferral of Pitch Upgrade 
    24 September 1996 - Additional Permanent Grandstands Estimate Review Meeting 
    26 September 1996 - Draft Cost Estimate for Additional Permanent Grandstands
    26 September 1996 - Rider Hunt Revision of Draft Cost Estimate for Additional Permanent
Grandstands 
    26 September 1996 - Rider Hunt Cost Estimate 

CHAPTER 11 - OCTOBER 1996 TO FEBRUARY 1997

    3 October 1996 - Mr Scott’s Advice to Soccer Federation about Loan Costs 
    4 October 1996 - SOCOG Reservations about Constrictions of Hindmarsh Stadium Site
    13 October 1996 - Launch of the Redevelopment 
    14 October 1996 - Execution of Funding Deed
    15 October 1996 - Start of on Site Construction Works for Stage 1 
    16 October 1996 - Selection of Practice Venues for Display to SOCOG 
    23 October 1996 - Finalisation of Stage 1 Loan Agreement and Deed of Guarantee 
    23 October 1996 - Executive Group Reassessment of Budget and Work Scope 
    24 October 1996 - Minister Ingerson’s Tip Off 
            Instructions to Woods Bagot
    27 October 1996 - Reimbursement of $300,000 to the Soccer Federation 
    28 October 1996 - Letting of Trade Packages for Construction 
    29 October 1996 - Visit by SOCOG Delegation 
            Key Issues 
            What the SOCOG Representatives said about Hindmarsh Stadium’s Chances 
            What the SOCOG Representatives said Needed to be Changed 
            What Minister Ingerson said was Proposed by way of Further Development 
    29 and 30 October 1996 - Announcement of Canberra and Melbourne Upgrades 
    6 November 1996 - Meeting of Bid Committee to Consider SOCOG Visit 
    14 November 1996 - Further Funds Required for Stage 1 
    18 November 1996 - Cabinet Approval of Submission for Stage 2 
    20 November 1996 - Additional Commitment to SOCOG 
    28 November 1996 - Premier Olsen 
    12 December 1996 - Change of Minister for Recreation, Sport and Racing 
    19 December 1996 - Renaming of the Office for Recreation, Sport and Racing 
    19 December 1996 - SOCOG Grant of Olympic Soccer to Adelaide 
    1 January 1997 - Formation of the City of Charles Sturt 
    7 January 1997 - Land Acquisition Impasse 
    8 January 1997 - Extension of National Portfolio Strategies’ Retainer 
    21 January 1997 - Ongoing Management Arrangements
    22 January 1997 - Complaint by the NSL Clubs about Financial Arrangements for Stage 1 
    28 January 1997 - Cabinet Approval of Revocation of Appointments as Parliamentary
Secretaries and New Appointments 
    10 February 1997 - Re-Establishment of Council Advisory Committee for
Hindmarsh Stadium 
    12 February 1997 - SOCOG Briefing 
    12 February 1997- First Draft of SOCOG Memorandum of Understanding 
    Late February 1997 - Cost of Hosting Olympic Soccer
    21 February 1997 - The Public Works Committee Informed of Increase from $8.125 million
to $8.685 million 
    24 and 25 February 1997 - Mr Ciccarello’s Dispute with the Government 

CHAPTER 12 - MARCH TO JUNE 1997 

    March 1997 - Study by the South Australian Centre for Economic Studies 
    March 1997 - Increase in Structural Steel Cost for Stage 1
    1 March 1997 - Mrs Hall’s Visit about Mr Ciccarello 
    3 March 1997- SOCOG Letter 
    7 March 1997 - Mr MacFarlane's fax to Mr Simmonds of SOCOG
    12 March 1997 - Mr MacFarlane’s Discussions with Queensland, Victoria and ACT 
    12 March 1997 - Stage 2 Formal Submission to Cabinet
    17 March 1997 - Establishment of Olympic Task Force 
    17, 18 and 19 March 1997 - Initial Meetings of Task Force 
    20 March 1997 - Checks on Conditions Precedent Stage 1 Documents
    25 March 1997 - Briefing of Attorney- General on Stage 2 Cabinet Submission 
    25 March 1997 - SOCOG Meeting
    27 March 1997 - Woods Bagot Update Compliance Matrix 
    17 April 1997 - Draft 2 of SOCOG Memorandum of Understanding 
    14 April 1997 - Woods Bagot Letter about Speculative Work 
    April 1997 - Extension of Options for Land Acquisition 
    1 May 1997 - Crown Solicitor’s Response to Interim Report of Public Works Committee
    9 May 1997 - Meeting with SOCOG 
    27 May 1997 - Agreement Between Soccer Federation and NSL Clubs as to Funding of Fit
Out 
    4 June 1997 - Services SA Report on Risk Management Issues 
    13 June 1997 - Start of Services SA’s Involvement in Stage 2 
    16 June 1997 - Cabinet Approval for the Purchase of Land in Hindmarsh Place
    23 June 1997 - NSL Clubs Licence Agreement 
    25 June 1997 - FIFA Approval of Five Venue Plan
    25 June 1997 - Draft 3 of SOCOG Memorandum of Understanding 
    25 June 1997 - Working Party for Draft Cabinet Submission 
    26 June 1997 - Services SA Comment on March 1997 Cost Estimate 
    30 June 1997 - Services SA Query of $16.205 million Budget

CHAPTER 13 - JULY TO NOVEMBER 1997 

    7 July 1997 - Cabinet Approval of Letter of Agreement with SOCOG 
    8 July 1997 - Briefing by Woods Bagot of Minister for Information and Contract Services 
    9 July 1997 - Fit Out Guarantee 
    14 July 1997 - Further Cabinet Consideration of Stage 2 
            Preparation of Submission 
            Content of the Submission
            Cabinet Resolution to Refer to Inter-Departmental Working Group 
    14 July 1997 - Meeting to Discuss Cabinet’s Concerns Over Stage 2 Proposal
    21 July 1997 - Cabinet Approval for Cabinet Committee and Project Director for Stage 2
    30 July 1997 - Public Works Committee Attention to Stage 2 
    5 August 1997 - Draft 4 of SOCOG Memorandum of Understanding 
    6 August 1997 - Letter from Council about Stage 2 
    6 August 1997 - Stage 2 Scope and Budget Workshop 
    11 August 1997 - Draft 5 of SOCOG Memorandum of Understanding 
    11 August 1997 - First Meeting of Hindmarsh Soccer Stadium Cabinet Committee 
    15 August 1997 - Final SOCOG Memorandum of Understanding 
    18 August 1997 - Cabinet Submission for Stage 2 
    25 August 1997 - Cabinet Approval of Further Increase in Expenditure for Stage 1 
    2 September 1997 - Second Meeting of Hindmarsh Soccer Stadium Cabinet Committee 
    4 September 1997 - Soccer Federation Business Plan 
    8 September 1997 - Cabinet Endorsement of Formal Submission of Stage 2 
    10 September 1997 - SOCOG Memorandum of Understanding Signed 
    17 September 1997 - Retainer of Woods Bagot for Stage 2 
    26 September 1997 - Fit Out Guarantee Deed 
    30 September 1997 - Draw Down of Stage 1 Loan 
    7 October 1997 - Amendment Deed and Fit Out Guarantee Deed 
    13 October 1997 - Council Concerns about Tenure 
    20 October 1997 - Ministerial Rearrangement
    23 October 1997 - Establishment of the Department of Industry and Trade 
    23 October 1997 - Establishment of the Department of Administrative and
Information Services 
    27 October 1997 - Strategic Value Management Study 
    28 October 1997 - NSL Clubs Unable to Contribute to Fit Out 
    30 October 1997 - Renaming of the Department of Administrative and Information Services 
    November 1997 – Auditor-General’s 1996/97 Annual Report 

CHAPTER 14 - DECEMBER 1997 TO SEPTEMBER 1998 

    6 December 1997 - Practical Completion of Stage 1 Works 
    17 December 1997 - Ministerial Rearrangement 
    January 1998 - Council Complaint about Use of Stadium for Rugby 
    February 1998 - NSL Clubs Difficulties in Paying Levies
    23 February 1998 - Cabinet Approval of Referral of Stage 2 to Public Works Committee 
    25 February 1998 - Definition of Stage 2 Works
    26 February 1998 - Submission to Public Works Committee of Stage 2
    4 March 1998 - Public Works Committee Hearings for Stage 2 
    6 March 1998 - Council Concerns about Ownership Issues 
    16 March 1998 - Third Meeting of Hindmarsh Soccer Stadium Cabinet Committee
    23 March 1998 - Mr Dixon’s Letter to the Public Works Committee 
    March 1998 - Ms White’s FOI Request 
    1 April 1998 - Public Works Committee Request for Further Information 
    2 April 1998 - Mr Ingerson’s Request to Mr Ciccarello for Information about the Bid 
    22 April 1998 - Mr Ingerson’s Letter to Public Works Committee about Stage 2
    30 April 1998 - Public Works Committee Interim Report on Stage 2 
    25 May 1998 - Mr Ingerson’s Response to Public Works Committee Interim Report 
    25 May 1998 - Mr Kowalick’s Response to the Public Works Committee Interim Report 
    16 June 1998 - The Public Works Committee Final Report on Stage 2 
    19 June 1998 - Briefing of Attorney-General on Land Ownership and Management Issues 
    24 June 1998 - Payment of Shortfall on 30 June 1998 Loan Instalment 
    29 June 1998 - Council Complaint over Use of Stadium for Rugby 
    21 July 1998 - Negotiations with Soccer Federation about Ownership of the stadium 
    27 July 1998 - Bowling Club Relocation 
    31 July 1998 - Fourth Meeting of Hindmarsh Soccer Stadium Cabinet Committee
    3 August 1998 - Resignation of Mr Ingerson as Minister for Industry, Trade and Tourism
    13 August 1998 - Adelaide City’s Further Complaint about the Cost of Playing at Hindmarsh 
    7 September 1998 - Adelaide City Proposal for Deferral of Levies or Fixed Fee 
    10 September 1998 – Soccer Federation Match Costs Cap at $13,000 
    15 September 1998 - Vacation of Bowling Club for Use as Site Office 
    21 September 1998 - Cabinet Approval of Baulderstone Hornibrook 
    29 September 1998 - Soccer Federation Proposal on Levies 
    29 September 1998 - Construction Agreement for Stage 2

CHAPTER 15 - OCTOBER 1998 TO AUGUST 2000 

    October 1998 - Cessation of Payment of Levies 
    8 October 1998 - Ministerial Appointments of Mrs Hall and Mr Evans
    28 October 1998 - Minister Evans Request for Meeting to Consider Increasing Levies
    31 October 1998 - Auditor- General’s 1997/98 Annual Report 
    5 November 1998 - Soccer Federation Submission Seeking Relief from Levies
    13 November 1998 - Fit Out Loan Repayment 
    27 November 1998 - Recognition that Government Not Able to Assess Soccer’s
Capacity to Pay 
    17 December 1998 - Charge over Levy monies
    31 December 1998 - Grandstand Loan Repayment Due 
    18 January 1999 - DIT Letter to Council 
    22 January 1999 - Minister Evans’ Agreement to Suspend Loan Repayments Pending
Arthur Andersen Report 
    25 March 1999 - Voluntary Administration of West Adelaide
    31 March 1999 - Arthur Andersen Report 
    June 1999 - Adelaide City Allegation that Licence Agreement Void 
    2 June 1999 - Public Works Committee Reconvene
    17 June 1999 - Council Letter about Naming Rights for Stadium 
    19 August 1999 - Hindmarsh Soccer Stadium Cabinet Committee
    23 August 1999 - Cabinet Approval 
    3 September 1999 - Hindmarsh Soccer Stadium Cabinet Committee Meeting
    7 September 1999 - Mortgage over the 1996 Lease
    10 September 1999 - Transfer of Responsibility for Staging Olympic Soccer
    22 September 1999 - Winding Up of West Adelaide
    1 October 1999 - Mrs Hall’s Resignation as Ambassador for Soccer
    7 October 1999 - Hindmarsh Soccer Stadium Cabinet Committee Meeting 
    8 October 1999 - Letter to the Soccer Federation
    8 October 1999 – Mr Pickard’s Letter to Mrs Hall
    15 October 1999 - Further Reduction in Match Fee for 1999/2000 
    18 October 1999 - Thompson Tregear Report
    20 October 1999 - Minister Evans’ Meeting with Soccer Federation
    25 October 1999 - Cabinet Committee Meeting 
    31 October 1999 – Auditor-General’s 1998/99 Annual Report 
    4 November 1999 - Minister Evans’ Meeting with the Soccer Federation
    5 November 1999 - Cabinet Committee Meeting
    8 November 1999 - Cabinet Authority to Acquire Ownership of the stadium
    9 November 1999 - Soccer Federation Letter to the Premier
    10 November 1999 - Transfer of Lease
    3 December 1999 - Practical Completion of Stage 2 Works
    13 December 1999 - Minister Evans’ Offer to the Council
    16 December 1999 - Minister Evans’ Offer to the Soccer Federation
    4 January 2000 - Minister Evans’ Requirement for a Response 
    14 February 2000 - Transfer of Office for Recreation and Sport 
    13 April 2000 - Cabinet Committee Meeting
    10 May 2000 - Cabinet Committee Meeting 
    24 May 2000 - Reduction in Match Fee for 2000-2001 NSL Season
    June 2000 - Adelaide City Relocation to Rams Park 
    23 and 27 June 2000 - Cabinet Committee Meetings 
    30 June 2000 - Letter from Council to Soccer Federation 
    1 August 2000 - Notice of Default for Unpaid Water 
    10 August 2000 - Cabinet Committee Meeting 
    11 August 2000 - Minister Evans’ Final Offer to the Soccer Federation 
    25 August 2000 - Caveat over 1996 Lease 
    31 August 2000 - Minister Evans’ Meeting with the Soccer Federation 

CHAPTER 16 - FROM SEPTEMBER 2000 

    6 September 2000 - Soccer Federation Request for Premier’s Intervention
    8 September 2000 - Revised Proposals for the Soccer Federation 
    September 2000 - Deputy Premier Kerin’s Assumption of Responsibility for
Hindmarsh Stadium 
    13-30 September 2000 - Staging of Olympic Matches 
    20 November 2000 - Further Letter from Council 
    11 December 2000 - Public Announcement of Adelaide City Plan to Purchase Rams Park
    11 December 2000 - Cabinet Approval for Resolution of Ownership and Management 
    21 December 2000 – Establishment of Office of Venue Management 
    3 January 2001 - Notice from Council Not to Use Certain Areas 
    22 January 2001 - Request for Payment of Unpaid Water Charges 
    29 March 2001 - Execution of Agreements Approved on 11 December 2001
    30 April 2001 - Cabinet Decision to Purchase Hindmarsh Stadium
    September 2001 - Negotiation of Purchase Contract 

Part 3
Detailed Findings on the Terms of Reference

CHAPTER 17 – INTRODUCTION TO PART 3 

    Overview of Part 3 
            Term of Reference I 
            Term of Reference II 
            Term of Reference III(a) 
            Term of Reference III(b) 
            Term of Reference IV 

CHAPTER 18 - DUE DILIGENCE IN STAGES 1 AND 2 

    Overview
    Scope of this Examination 
            Section 32 of the Public Finance and Audit Act 1987 
            The Hindmarsh Soccer Stadium (Auditor-General’s Report) Act 2001 
            The "Project" 
            Efficiency and Cost-Effectiveness
    Definition of Due Diligence 
            Due Diligence Generally 
            The Substance of Due Diligence
                Compliance 
                Benefits or Needs 
                Risks 
    Specific Requirements Applicable to Public Projects 
            Legislative Requirements 
                Parliamentary Committees Act 1991 
                Public Finance and Audit Act 1987 
            Government Internal Guidelines 
                Treasurer’s Instructions
    Who Performs Government Due Diligence 
            Preface
            Government Advisory Agencies 
                The Crown Solicitor’s Office 
                The Department of Treasury and Finance 
                The Department of Premier and Cabinet 
            Access to Other Expertise 
                DAIS 
                Resources External to the Government 
                The Process of Briefing Other Agencies
    How this Examination has Applied the Definition of Due Diligence
            "Signed Agreements for Construction" and "Commitment" 

CHAPTER 19 – STAGE 1 PROJECT INITIATION AND APPROVAL 

    Overview
    Feasibility Studies and Cost Benefit Analyses
            Objectives of the Redevelopment 
                Mandatory Identification of Objectives 
                Identification of Objectives as Part of a Feasibility Study 
                No Comprehensive Statement of Objectives Exists for Stage 1 
                Statements of Objectives in Cabinet Submissions 
                Summary of Objectives 
            Early Feasibility Studies 
            No Reliance Upon or Updating of Earlier Studies 
            Inadequate Commissioning of Feasibility Studies 
                SACON Preliminary Feasibility Estimate 
                Woods Bagot Preliminary Design Work
                Ernst & Young Report 
            Omissions from Studies 
            The Fit Out Guarantee 
                Previous Arrangements for Fit Out 
                Cabinet Submission for Fit Out Guarantee 
            Significance of Policy Decision
            Conclusion on Inadequacy of Feasibility Studies
    Cabinet Submissions Inadequate Basis for Cabinet Decisions 
            Overview 
            Cabinet’s Role Generally 
            Cabinet Submissions
                Submissions a Summary of Deliberations 
                Even-Handedness of Discussion 
                Realistic Set of Options 
                Inadequate Consultation with Central Agencies 
                Inadequate Content of April 1996 Submission
                Inadequate Content of August 1996 Submission 
                Inadequacy of July 1997 Submission 
                Conclusion about Stage 1 Cabinet Submissions
    Inadequate Definition of FIFA/SOCOG Requirements
            Instructions to Woods Bagot about FIFA Requirements
            Failure to Analyse Requirements Received from SOCOG 
            Omission of Pitch Upgrade 

CHAPTER 20 – PUBLIC WORKS COMMITTEE PROCESS FOR STAGE 1 

    Overview 
    Inadequate Information about FIFA/SOCOG Requirements Provided to the Public
Works Committee 
            Written Submission to the Public Works Committee 
            True Position on Satisfaction of Olympic Requirements 
            Public Works Committee Erroneous Conclusion in 33
rd Report 
    Incomplete Advice of the Crown Solicitor's Office Provided to the Public Works Committee 
            Satisfaction of Conditions Imposed by the Public Works Committee 
            Conclusion on the Stage 1 Public Works Committee Process 

CHAPTER 21 - DIRECTION AND CONTROL OF STAGE 1 

    Overview 
    Committee Structure
            Definition of Committee Roles and Functions and Reporting Requirements 
                Committees Set Up Under Minister Oswald 
                Committees Set Up by Minister Ingerson 
            Inappropriate Membership of Committees
            Lack of Control 
    Inadequate Application of Agency Advice 
            Advice Given But Not Acted Upon 
                The Crown Solicitor’s Office Advice about the 1996 Treasurer’s Guarantee 
                The Crown Solicitor's Office’s Advice about Negotiating Funding Deed 
                The Crown Solicitor's Office’s Advice about Content of August
                Cabinet Submission 
                The Crown Solicitor's Office Advice about Ownership and Management 
            Inadequate Instructions Given
                April 1995 Memorandum of Understanding with the Soccer Federation 
                Preparation of the Funding Deed in 1996 
            Inadequate Advice Given 
                Failure to Identify Legislative Requirements 
                Failure to Identify Non-Compliance with Internal Government Guidelines 
                Poor Advice about Ownership and Management Structures
                Failure to Attend to Prudential Matters that had been Identified 
            Advice Not Sought 
                April 1996 Cabinet Submission 
                No Advice Sought about Other Measures to Protect Achievement of the
Government’s Objectives
                Ensuring that the NSL Clubs Would Use the Stadium
            Conclusion on Role of Central Agencies and Services SA 

CHAPTER 22 - FAILURE TO RESOLVE OWNERSHIP AND MANAGEMENT FOR STAGE 1 

    Overview 
    Warnings that Ownership Critical to Protecting Public Investment 
    Inadequate Protection Adopted 
            Ensuring that the Council as Owner of the Land did not Prevent the stadium from
being Available for Playing Soccer 
            Ensuring that Hindmarsh Stadium was Managed so as to Maximise its Use
for Soccer
    Recommended Protection Disregarded 
            April 1995 Memorandum of Understanding
            Funding Deed 
                Failure to Secure a Mortgage Over the 1996 Lease 
                Failure to Execute the Charge Over the Levy monies until December 1998
                Failure to Monitor Soccer Federation Obligations under Funding and
Fit Out Deeds
    Conclusion on Issue of Ownership and Management 

CHAPTER 23 – STAGE 2 PROJECT INITIATION AND APPROVAL 

    Overview 
    Feasibility Studies and Cost Benefit Analyses
            Stated Approach of SACES Study
            Limitations of Data Utilised in SACES Study 
            Exclusions from the Study 
            Criticism of the Study by the Department of Treasury and Finance
            No Attempt to Update or Refine SACES Study in Light of Further Information
            Woods Bagot Master Planning Process 
                The Future Need for an Enlarged Facility 
                The Cost of Keeping Open the Soccer Federation’s Options for Future
Development 
                The Soccer Federation’s Ability to Meet the Cost of Upkeep of an Enlarged
Facility
                The Possibility of an Unstaged Redevelopment 
            Conclusion on Inadequacy of Feasibility Studies and Cost Benefit Analyses
    Alternatives to the Development were Disregarded
            Less Expensive Development 
            Postponing Stage 1 to Amalgamate it with Stage 2 
            Use of a Different Venue 
            Conclusion on Failure to Investigate All Feasible Options 
    Premature Commitments to Land Acquisition
            Conclusion on Premature Commitment to Land Acquisition
    SOCOG Bid Mishandled 
            Failure to Clarify SOCOG’s Criteria for Selection of Venues
                Conclusion on Failure to Clarify Selection Criteria 
            Informal and Imprecise Communications 
                Introduction 
                Informal Intimation About Site Constriction 
                Minister Ingerson’s Tip Off by a Senior SOCOG Official 
                29 October 1996 SOCOG Visit
                Conclusion on Informal Communications
            Composition of Bid Committee
                Conclusion on Composition of Bid Committee 
    Inappropriate Process for Setting Budget for Stage 2
            Overview
            Budget Set by Reference to Abandoned "Soccer Park" Concept 
            Budget Not Set by Reference to Concerns of SOCOG
            Change to Permanent Stands 
            Arbitrary Budget for Bowling Club Relocation 
            Conclusion on Inappropriate Method of Setting Budget
    Cabinet Submissions Inadequate Basis for Cabinet Decisions
            Overview 
            Breach of Treasurer’s Instruction 9105 
            Inadequate Content 
                Overview
                13 November 1996 Cabinet Submission
                12 March 1997 Cabinet Submission
                9 July 1997 Cabinet Submission
                15 August 1997 Cabinet Submission 
                4 September 1997 Cabinet Submission 
                16 February 1998 Cabinet Submission 
                Conclusion on Inadequate Cabinet Submissions

CHAPTER 24 – STAGE 2 PUBLIC WORKS COMMITTEE PROCESS 

    Overview
            Inadequate Content of Original Submission 
                Overview 
                Funding Arrangements
                The Council’s Contribution to the Funding Arrangements for the Project 
                SOCOG’s Requirements for the Upgrade 
                The Reasons for the Content of Stage 2 
                The Process Used for the Design of Stage 2 
                Arrangements for Ownership and Management 
                Conclusion about Submission to Public Works Committee
            Failure to Provide Information about SOCOG 
                Interim Report
                Cabinet Confidentiality
                Conclusion on Inadequate Responses to Public Works Committee Reports
            Parliamentary Resolution that the Public Works Committee Table Its Report 
                Conclusion on Parliamentary Resolution 

CHAPTER 25 – DIRECTION AND CONTROL OF STAGE 2 

    Overview 
    Work Critical to Stage 2 was Undertaken through Stage 1 Structure 
            Excessive Access of the Soccer Federation to the Government’s Resources 
                Conclusion on the Soccer Federation’s Access to Government Resources
            The Soccer Federation Role on the Bid Committee
                Conclusion on Composition of Bid Committee
    Project Management Structure
            Deputy Premier Ingerson as Proponent Minister 
            Minister Evans as Responsible Minister 
            Conclusions on Project Management Structure
    Inadequate Application of Agency Advice 
            Overview 
            Agencies Advice Disregarded 
            Inadequate Advice Given 

CHAPTER 26 - FAILURE TO RESOLVE OWNERSHIP AND MANAGEMENT DURING STAGE 2 

    Overview 
    Ownership and Management Must be Resolved Before Commitment 
    Government Recognition of the Importance of the Ownership Issue 
            Nature of the Issues 
            March 1997 Cabinet Submission 
            July 1997 Cabinet Submission on SOCOG Letter of Agreement 
            July 1997 Cabinet Submission for Stage 2 
            Referral to Inter-Departmental Working Group 
            August 1997 Cabinet Submission 
            September 1997 Cabinet Submission 
            February 1998 Cabinet Submission 
    No Position Adopted Until Stadium Nearly Complete 
    No Proper Analysis of Legal Risks 
    No Proper Analysis of Financial or Economic Factors 
    Conclusion on Failure to Address Ownership and Management 

CHAPTER 27 – UNDUE PRESSURE ON SPORTING CLUBS OR ASSOCIATIONS 

    Overview 
    Relevance of this Chapter 
    Definition of Undue Pressure 
    The Legal Commitments made by the Soccer Federation 
    The Legal Commitments of the NSL Clubs 
            The Adelaide City Club Rooms and Loan Agreement 
            The 1995 Clubs Memorandum of Understanding 
            May 1995 and May 1996 Authorisation by the Council of Clubs 
            The 1996 Licence Agreements 
            The 1997 Licence Agreement 
    Later Complaints about the Cost of Playing at Hindmarsh 
    Conclusion 

CHAPTER 28 - DETAILED FINDINGS ON TERM OF REFERENCE III(b) 

    Overview 
            Chapter 29 - Historical Overview of Legal Documents 
            Chapters 30 to 34 - Present Status of Legal Documents 
            Chapter 35 – Financial Status of the Signatories and Creation of Financial Difficulty
by Legal Documents 

CHAPTER 29 - HISTORICAL OVERVIEW OF LEGAL DOCUMENTS 

    Introduction 
    Legal Documents Prior to April 1995 
    The April 1995 Memoranda of Understanding 
    Stage 1 Project Documents 
    Fit Out of Stage 1 
    The Acquisition of Land Surrounding Hindmarsh Stadium 
    Stage 2 and the Hosting of Olympic Soccer at Hindmarsh Stadium 
    Current Arrangements for Ownership and Management 
            Purchase of Hindmarsh Stadium Site 
            Soccer Federation Agreement 
            Adelaide City Agreement 

CHAPTER 30 - PRESENT STATUS OF LEGAL DOCUMENTS PRIOR TO APRIL 1995 

    The 1981 Lease 
    The 1994 Ground Management Agreement 
            Parties, Execution Status, Enforceability and Purpose 
            Key Terms 
            Currency 
    The Adelaide City Club Rooms and Loan Agreement 
            Parties, Execution Status and Purpose 
            Enforceability and Currency 
            Key Terms 

CHAPTER 31 – PRESENT STATUS OF APRIL 1995 MEMORANDA OF UNDERSTANDING 

    The April 1995 Memorandum of Understanding 
            Parties and Execution Status 
            Enforceability 
            Currency 
            Overview of Key Terms 
            Conditions Precedent and Status of Performance 
            Ownership and Control 
            Construction Obligations 
            Funding 
            Reporting and Accountability 
    The NSL Clubs Memorandum of Understanding 
            Parties and Execution Status 
            Enforceability 
            Currency 
            Key Terms 

CHAPTER 32 – PRESENT STATUS OF THE STAGE 1 PROJECT DOCUMENTS 

    Engagement of the Department for Building Management 
    Woods Bagot Consultancy Agreement for Stage 1 
            Parties, Execution Status, Enforceability and Currency 
            Key Terms 
    The 1996 Lease 
            Parties and Execution Status 
            Enforceability and Currency 
            Key Terms – The Lease Schedule 
            Key Terms – The Lessee’s Covenants 
            No Government Approval of Terms 
            Hindmarsh Stadium Site Now Greater than Land in 1996 Lease 
            Caveat by the Treasurer 
    Stage 1 Construction Management Agreement 
            Parties, Execution Status and Enforceability 
            Currency and Status of Performance 
    The 1996 Licence Agreements 
            Parties and Execution Status 
            Enforceability 
            Currency 
            Key Terms 
    The Stage 1 Funding Deed 
            Parties 
            Enforceability and Currency 
            Key Terms and Status of Performance 
                Scope of the Redevelopment 
                Project Costs 
                Funding 
                Grandstand Levy 
                Treasurer’s Guarantee 
                Free Tickets 
                Charge over the $3 Levy monies 
                1996 Lease 
                Mortgage of the 1996 Lease 
                Licences from the NSL Clubs 
                Letter from Soccer Australia 
                Premier League Matches 
                Role of the Minister for State Government Services 
                Establishment of the Stadium as a Separate Profit Centre 
                Records of Match Attendances 
                Management Committee 
                Record Keeping, Audit, Provision of Information and a Business Plan and
Annual Reporting 
                Promotion of Soccer and Best Use of the Stadium 
                Insurance 
                Good Repair 
                Events of Default 
    Stage 1 Loan Agreement 
            Parties and Execution Status 
            Key Terms and Status of Performance 
    The 1996 Guarantee 
            Parties and Execution Status 
            Enforceability and Currency 
            Key Terms and Status of Performance 
    The Stage 1 Minister’s Licence Agreement 
            Parties, Execution Status and Purpose 
            Enforceability and Currency and Status of Performance 
    The 1997 Licence Agreement 
            Parties and Execution Status 
            Enforceability and Currency 
            Key Terms and Changes to the 1996 Licence Agreements 
    Variations of the 1997 Licence 
            Fit Out 
            Licence and Levy Payments 
    The Charge over the Levy Monies 
            Parties, Execution Status and Enforceability 
            Purpose 

CHAPTER 33 – PRESENT STATUS OF LEGAL DOCUMENTS FOR FIT OUT OF STAGE 1 

    The Fit Out Guarantee Deed 
            Purpose and Execution Status 
            Enforceability and Currency 
            Key terms and Status of Performance 
                Scope of the Fit Out 
                Funding 
                Marketing and Advertising Expenditure 
                Treasurer’s Guarantee 
                Charge over the Levy monies 
                Reporting Obligations 
                Events of Default 
    The Fit Out Loan 
    The Fit Out Guarantee 
            Parties and Execution Status 
            Enforceability and Currency 
            Key Terms and Status of Performance 

CHAPTER 34 – PRESENT STATUS OF LEGAL DOCUMENTS FOR THE ACQUISITION OF LAND SURROUNDING HINDMARSH STADIUM 

    Retainer to Undertake a Strategy Overview 
    Letter of Appointment 
    Option Agreements 
            3 Hindmarsh Place – Azzuri Club Land 
            3A Hindmarsh Place – former Christian Church 
            6 Hindmarsh Place – Anglican Church 
            15A Richard Street – Flexbane & Nib Nominees 
    Contracts for Purchase of Land 

CHAPTER 35 – PRESENT STATUS OF LEGAL DOCUMENTS FOR STAGE 2 AND HOSTING OLYMPIC SOCCER AT HINDMARSH STADIUM 

    July 1997 SOCOG Letter of Agreement 
            Parties and Execution Status 
            Enforceability and Currency 
    The Olympic Memorandum of Understanding 
            Execution Status 
            Enforceability and Currency 
            Key Terms 
            Physical Requirements 
            Organisation and Conduct of Matches 
            Cost 
            Revenue 
    SOCOG Marketing Agreement 
            Parties and Execution Status 
            Enforceability and Currency 
            Key Terms 
    Stadium Use Deed 
            Execution Status, Enforceability and Currency 
            Key Terms 
    Woods Bagot Consultancy Agreement for Stage 2 
            Parties, Execution Status, Enforceability and Currency 
            Key Terms 
    Stage 2 Construction Management Agreement 
            Parties, Execution Status and Enforceability 
            Currency and Status of Performance 
    Stage 2 Minister’s Licence Agreement 
            Parties, Execution Status and Purpose 
            Enforceability, Currency and Status of Performance 
    The Stage 2 Council Licence 
            Parties, Execution Status and Purpose 
            Enforceability, Currency and Status of Performance 
    Relocation of Hindmarsh Bowling Club 
    Meals on Wheels Relocation 
            1957 Lease 
            Relocation Proposals 
            Contract for Sale and Purchase of 52 Manton Street 
            Construction of New Kitchen Building 
            Deed of Surrender of Lease 
            Relocation Deed 
    Belarusian Church Relocation Deed 
    Compensation Agreements with Adjacent Landowners 

CHAPTER 36 - FINANCIAL STATUS OF THE SIGNATORIES AND CREATION OF FINANCIAL DIFFICULTY BY LEGAL DOCUMENTS 

    Financial Status of the Soccer Federation 
    Financial Status of Adelaide City 
    Financial Status of West Adelaide 
    Creation of Financial Difficulty by Legal Documents 
            Soccer Federation 
            Adelaide City 
            West Adelaide 

CHAPTER 37 – DETAILED FINDINGS ON TERM OF REFERENCE IV 

    Introduction 
            Conflicts of Interest 
            Imprudent or Improper Behaviour 
            Appropriate Processes 

CHAPTER 38 - CONFLICTS OF INTEREST OF GOVERNMENT REPRESENTATIVES 

    Overview 
    Relevant Principles 
    Mrs Hall – Overview of her Various Roles 
            Mrs Hall – Ambassador for Soccer in South Australia 
            Mrs Hall – Parliamentary Secretary 
                Terms of Appointments 
                Duties as a Parliamentary Secretary 
            Mrs Hall – Chair of the Stage 1 Redevelopment Committee 
                Formal Definition of Mrs Hall’s Role 
                The Minister’s View of Mrs Hall’s Role 
                Mrs Hall’s View of Her Role 
                Mrs Hall’s Conflict of Interest and Duty as Chair of the Stage 1
Redevelopment Committee 
                Mrs Hall’s Conflict of Interest and Duty as a Minister of the Crown 
                Mrs Hall’s Conflict of Duties as a Member of Parliament and a Parliamentary Secretary 
            Mrs Hall – Soccer 2000 Bid Committee 
            Mrs Hall – SA Olympic Football Taskforce 
            Mrs Hall – Stage 2 Reference Group 
            Mrs Hall - Conclusion 

CHAPTER 39 - CONFLICTS OF INTEREST OF NON-GOVERNMENT PERSONS 

    The Soccer Federation 

CHAPTER 40 – APPROPRIATE PROCESSES 

    Overview 
    The Planning Stages of the Project 
            Overview 
            Inadequate Feasibility Studies 
            Cabinet Submissions Inadequate Basis for Cabinet Decision 
            Inadequate Definition of FIFA/SOCOG Requirements 
            No Legal Relationship Between the Government and the NSL Clubs 
            Failure to Resolve Ownership and Management Issues 
    The Awarding and Monitoring of Consultancies 
            Irregular Retention of Primary Consultant for Stage 1 
                Overview 
                Terms of Woods Bagot’s Consultancy Agreement 
            Mr Ciccarello’s Appointment 
    Irregular Retainer of Primary Consultant for Stage 2 
            Overview 
            Work Prior to Formal Retainer for Stage 2 
            Formal Retainer of Woods Bagot for Stage 2 
    National Portfolio Strategies 
    Rider Hunt 
    The Tendering Process and the Letting of Contracts 
            Overview 
            Sponsorship 
                Inappropriate Selection Process 
    The Construction of the Stadium 
            Stage 1 
            Stage 2 
    The Ongoing Management of the Stadium 

APPENDICES

APPENDIX 1 – THE COST OF THE REDEVELOPMENT 

    Table 1 – Capital Cost 
    Table 2 – Repayment of Soccer Federation Loans 
    Table 3 – Total Government Exposure 
    Table 4 – Detailed Capital Cost 
    Table 5 – Increases made to the Stage 1 Budget 
    Table 6 – Increases made to the Stage 2 Budget 
    Table 7 – Repayments of Stage 1 Loan to 30 June 2001 
    Table 8 – Repayments of Fit Out Loan to 30 June 2001 
    Table 9 – Guarantee Fee Payable to the Treasurer 

APPENDIX 2 – SPECTATOR ATTENDANCES AND LEVIES PAYABLE UNDER FUNDING AND FIT OUT DEED AND LEVIES WAIVED OR SUSPENDED 

    Table 1 – 7 December 1997 to 30 September 1998 
    Table 2 – 1 October to 31 December 1998 and 1 January to 30 September 1999 
    Table 3 – 1 October 1999 to 30 September 2000 
    Table 4 – Summary 
    Table 5 – Average Attendances at NSL Matches at Hindmarsh Stadium from 1991/1992
to 1998/1999 

APPENDIX 3 – THE COST OF HOSTING OLYMPIC SOCCER AT HINDMARSH STADIUM 

APPENDIX 4 – CONCEPT AND SITE PLANS OF HINDMARSH STADIUM 

    Plan 1 – Hindmarsh Stadium - Site Plan - 1995 
    Plan 2 – Hindmarsh Stadium Site Plan – 1989 – Used as Annexure A to April 1995
Memorandum of Understanding 
    Plan 3 – Option One from 1989 SACON Feasibility Study - Used as Annexure B to
April 1995 Memorandum of Understanding 
    Plan 4 – Woods Bagot Plan - Option C – March 1996 
    Plan 5 – Woods Bagot Plan - Option D – March 1996 
    Plan 6 – Master Plan submitted to SOCOG in September 1996 as Part of Adelaide’s Bid 552
    Plan 7 – New Concept Plan Submitted to SOCOG on 20 November 1996 
    Plan 8 – Option 1 – 12 March 1997 Cabinet Submission 
    Plan 9 – Option 2 – 12 March 1997 Cabinet Submission 
    Plan 10 – Hindmarsh Stadium - Titles Plan - November 1999 

APPENDIX 5 – EXPLANATION OF "FIFA REQUIREMENTS" 

    Introduction 
    FIFA Generic Publications 
            Laws of the Game 
            Authorisation of Temporary Stands in Stadia 
            Non-binding Technical Recommendations 
    Sydney 2000 Guidelines 
            Football Stadia Minimum FIFA Requirements 
            Olympic Games Football Tournament FIFA/SOCOG Requirements 
    Indirect Evidence of FIFA Requirements 
            1993 World Youth Championships 
            Initial Negotiations with the Soccer Federation for Further Upgrade 
            Preliminary Costing of Further Development 
            Initial Negotiations with SOCOG for Hosting of 2000 Olympic Soccer Tournament 
            Woods Bagot Preliminary Examination of FIFA Requirements 
            July 1996 Statement of Requirements 
            29 October 1996 - "Legacy for Sport"